When a factory fire broke out in Derrimut, Melbourne’s west, it quickly became one of the largest fires the state has seen in recent years. More than 180 firefighters responded to the scene on Swann Drive, battling the blaze fueled by hazardous materials like kerosene, fuel, and ethanol. The fire, which started around 11:20am on
A wet well primarily serves as a large containment system for wastewater, providing a temporary storage solution before its transfer to a treatment facility or another designated area. Due to various reasons such as system inefficiencies, significant rainfall, or regular maintenance tasks, water can accumulate in these wells. Addressing such a challenge, CSA embarked on
CSA was engaged to assist in a hydro excavation project in East Melbourne as part of an ongoing project. The work involved, Non Destructive Digging and Excavating, waste eduction and waste transportation to the disposal site. two operators were sent to the field with two Hydro Excavation units. They managed to complete the NDD work
CSA was engaged to assist in an excavation project which consisted of repairing a leak on a 1350mm water main as well as safely removing a 1200mm barrel drain for repairs to be comepleted. This project was required local Stormwater drains and pits being reconstructed before total reinstatement could be completed. With the weather being
Industrial waste management control can be complex and challenging. We have recently implemented a field management system that allows us to apply a cloud-based technology across all our locations to manage our fleet, equipment, and resources efficiently and in a timely manner. We have invested heavily in our field management system to ensure that we
CSA were engaged to unblocking a large SWD pipe in early June 2019. The Open channel drain had not been maintained for many years causing the 900mm diameter SWD pipe under the road to silt up and become 90% blocked. The drain could not flow to its full capacity causing flooding upstream of this pipe.
In order to create better connectivity for pedestrians and cyclists in High street, the Reservoir level crossing project started in early January. This project is aiming to replace the level crossing with a rail bridge over High street. The project also involves the rebuilding of Reservoir train station. The boom gates at this busy street
The Victorian Government’s Level Crossing Removal project has announced the removal of 50 of Melbourne’s dangerous and congested level crossings by 2022, with at least 20 of these removed by 2018. This will bring improved traffic flow, safer paths and better connections for pedestrians and cyclists in Victoria. The Western Program Alliance (WPA) is currently
With Utility Locating, Hydro Excavation, Surveying and Road Reinstatement’s stretching from Fitzroy North to the Melbourne Cricket Ground, this will certainly be a project to remember. We are coming to an end of one of our larger projects, which began 4th of March, stretching five kilometres away from Fitzroy North and went right down to
Working with liquid waste isn’t always as glamorous as it’s cracked up to be. Some of our new operators discovered the truth of working at a treatment plant in February. Six of our skilled operators and labourers spent four days in February at a treatment plant in the outer suburbs of Victoria. We enjoy our